AS 09.45.886. Procedure After Inspection.
Within 14 days after completion of an inspection made under AS 09.45.885, the construction professional shall serve on
the claimant a written
- (1) offer to repair the defect without charge to the claimant; the offer must include a report of the scope of the
inspection, the findings and results of the inspection, a description of any repairs necessary to repair the defect,
and a schedule for the completion of the repairs;
- (2) offer to compromise and settle the claim by a payment of money under AS 09.45.882
(b)(2); or
- (3) statement that the construction professional will not repair the defect.
Note to HTML Version:
This version of the Alaska Statutes is current through December, 2004. The Alaska Statutes were automatically converted to HTML from a plain text format. Every effort
has been made to ensure their accuracy, but this can not be guaranteed. If it is critical that the precise terms of the Alaska Statutes be known, it is recommended that more formal sources be consulted. For statutes adopted after the effective date of these statutes, see, Alaska State Legislature
If any errors are found, please e-mail Touch N' Go systems at E-mail. We
hope you find this information useful.
Last modified 9/3/2005