(a) Except as modified under 11 AAC 110.270, the consistency review process shall be completed within 30 or 50 days after the start date set under 11 AAC 110.235.
(b) A project is subject to a 30-day consistency review if all required authorizations for the activities, as identified in the C List, are listed as authorizations subject to a 30-day review.
(c) Except as provided in (b) of this section, a project is subject to a 50-day consistency review.
History: Eff. 7/1/2004, Register 170
Authority: AS 46.39.010
Note to HTML Version:
The Alaska Administrative Code was automatically converted to HTML from a plain text format. Every effort has been made to ensure its accuracy, but neither Touch N' Go Systems nor the Law Offices of James B. Gottstein can be held responsible for any possible errors. This version of the Alaska Administrative Code is current through June, 2006.
If it is critical that the precise terms of the Alaska Administrative Code be known, it is recommended that more formal sources be consulted. Recent editions of the Alaska Administrative Journal may be obtained from the Alaska Lieutenant Governor's Office on the world wide web. If any errors are found, please e-mail Touch N' Go systems at E-mail. We hope you find this information useful. Copyright 2006. Touch N' Go Systems, Inc. All Rights Reserved.
Last modified 7/05/2006