Title 11 . Natural Resources
Chapter 110 . District Coastal Management Plan Requirements
Section 210. Pre-review assistance

11 AAC 110.210. Pre-review assistance

(a) Before the start of a consistency review, a coordinating agency shall, on request, assist an applicant by providing information about the consistency review requirements.

(b) At the time an applicant requests pre-review assistance under this section, the applicant shall, at a minimum, provide a brief description of the proposed project. To the extent feasible, the applicant shall provide the coordinating agency with a

(1) completed coastal project questionnaire;

(2) map identifying the location of the project and adjacent facilities; and

(3) description of any man-made structures or natural features that are at or near the project site.

(c) If requested by the applicant, the coordinating agency shall provide information including

(1) information about the coastal project questionnaire and the consistency review process;

(2) preliminary identification of coastal resource districts that may have an interest in the project;

(3) to the extent feasible, preliminary identification of applicable enforceable policies of the program;

(4) preliminary identification of the state and federal authorizations likely required for the project and individuals, if known, to contact in other state or federal agencies;

(5) to the extent feasible, preliminary identification of the activities that may require a resource agency authorization or that may require a federal authorization listed under 11 AAC 110.400;

(6) to the extent feasible, an estimated time schedule for the consistency and resource agency authorization reviews; and

(7) to the extent feasible, preliminary identification of information that may be required to determine consistency with the enforceable policies of the program, compliance with resource agency authorizations, and potential mitigation requirements.

(d) If the applicant requests pre-review assistance under this section,

(1) the coordinating agency may consult with resource agencies and the office as necessary to assist the coordinating agency in developing the information described in (c) of this section; and

(2) a resource agency may identify issues related to the authorization and potential mitigation requirements and, to the extent feasible, discuss with the applicant how the activity may comply with the agency's statutory and regulatory authorities.

(e) The coordinating agency shall inform a coastal resource district of a proposed project that may affect a coastal use or resource within the district. If a pre-review assistance meeting is scheduled, the coordinating agency shall invite a representative from any potentially affected coastal resource district to the meeting.

History: Eff. 7/1/2004, Register 170

Authority: AS 46.39.010

AS 46.39.030

AS 46.39.040

AS 46.40.040

AS 46.40.096


Note to HTML Version:

The Alaska Administrative Code was automatically converted to HTML from a plain text format. Every effort has been made to ensure its accuracy, but neither Touch N' Go Systems nor the Law Offices of James B. Gottstein can be held responsible for any possible errors. This version of the Alaska Administrative Code is current through June, 2006.

If it is critical that the precise terms of the Alaska Administrative Code be known, it is recommended that more formal sources be consulted. Recent editions of the Alaska Administrative Journal may be obtained from the Alaska Lieutenant Governor's Office on the world wide web. If any errors are found, please e-mail Touch N' Go systems at E-mail. We hope you find this information useful. Copyright 2006. Touch N' Go Systems, Inc. All Rights Reserved.

Last modified 7/05/2006