Chapter 95 . (No Regulations Filed)
Section 230. Change in operations

11 AAC 95.230. Change in operations

(a) An operator shall notify the state forester of a change in operations from those described in the finalized detailed plan of operations that is likely to cause significant adverse impact to fish habitat or surface water quality. Changes in operations that require agency review include:

(1) a new or reconstructed bridge, road segment, or material disposal site that crosses surface waters, abuts a riparian area; or is on unstable soils;

(2) a new or modified activity in a riparian area; or

(3) the ten acres or more increase of a cutting unit.

(b) Upon receipt of a notice of a change in operations, the division will promptly review the proposed change, either in the field or in the office, and notify the operator of the time required for complete review. The division may take up to fifteen days for its review.

(c) The state forester will coordinate the review with the other agencies. A review of a change and an agency decision made under this section will be conducted in accordance with AS 41.17.098 . If the state forester determines that a change in operations is a substantial change, the operator shall revise the detailed plan of operations and submit it to the state forester for review under 11 AAC 95.220 and 11 AAC 95.225.

(d) An operator shall promptly inform the state forester when a previously unknown anadromous fish water body is discovered within an area covered by a detailed plan of operations. The state forester will review the activities to be conducted within the riparian area of that water body in accordance with (b) of this section; however, discovery of such a water body will not be considered a substantial change. Operations in the vicinity of a newly discovered anadromous water body must be consistent with other regulations of this chapter, including 11 AAC 95.265(e) .

(e) In this section, "substantial change" means a change in operations of sufficient scope so as to require a full 30-day review; "substantial change" includes the inclusion of a new harvest unit and the construction of a road accessing a new area; "substantial change" does not include a change made in response to an agency request, or a change made in response to field conditions that is intended to accomplish an operation included in the detailed plan of operations.

History: Eff. 6/10/93, Register 126

Authority: AS 41.17.010

AS 41.17.055

AS 41.17.080

AS 41.17.090

AS 41.17.098


Note to HTML Version:

The Alaska Administrative Code was automatically converted to HTML from a plain text format. Every effort has been made to ensure its accuracy, but neither Touch N' Go Systems nor the Law Offices of James B. Gottstein can be held responsible for any possible errors. This version of the Alaska Administrative Code is current through June, 2006.

If it is critical that the precise terms of the Alaska Administrative Code be known, it is recommended that more formal sources be consulted. Recent editions of the Alaska Administrative Journal may be obtained from the Alaska Lieutenant Governor's Office on the world wide web. If any errors are found, please e-mail Touch N' Go systems at E-mail. We hope you find this information useful. Copyright 2006. Touch N' Go Systems, Inc. All Rights Reserved.

Last modified 7/05/2006