An application submitted under 18 AAC 75.523 must include the following information:
(1) the applicant's name, address, and telephone number, and any facsimile number;
(2) the role of the response planning facilitator, as described in 18 AAC 75.428(a) (1) or (2);
(3) as applicable under 18 AAC 75.428(a) (2), a current list of nontank vessel cleanup contractors with which the applicant has a contract, or of which the applicant is a member, and a statement, signed by the response planning facilitator and each nontank vessel cleanup contractor, that the nontank vessel cleanup contractor will respond on behalf of a plan holder who enters into a contract or membership agreement with the response planning facilitator to meet the requirements of 18 AAC 75.400 - 18 AAC 75.496;
(4) as applicable under 18 AAC 75.428(a) (2), a current list of each nontank vessel incident management team with which the applicant has a contract, and a statement, signed by the response planning facilitator and each nontank vessel incident management team, that the nontank vessel incident management team will respond on behalf of a plan holder who enters into a contract with the response planning facilitator to meet the requirements of 18 AAC 75.400 - 18 AAC 75.496;
(5) as applicable under 18 AAC 75.428(a) (2), a current list of each nontank vessel plan in which the applicant is identified as the contracted response planning facilitator, the number of vessels covered by each of those plans, each region of operation of each vessel covered by each plan, and the largest vessel response planning standard volume for each plan;
(6) as applicable under 18 AAC 75.428(a) (2), a statement, signed by the response planning facilitator, that each contract will obligate the response planning facilitator to
(A) activate the appropriate response resources if a discharge occurs;
(B) notify the plan holder immediately if the response planning facilitator cannot carry out the obligations specified in the contract; and
(C) give written notice at least 30 days before terminating the contract with the plan holder;
(7) a certification, under penalty of unsworn falsification in violation of AS 11.56.210 , that the statements made in the application are correct to the best of the applicant's knowledge;
(8) an acknowledgment that knowingly providing false information, or a demonstrated inability to maintain the appropriate response planning facilitation services listed in the application, may result in the revocation of registration.
History: Eff. 11/27/2002, Register 164
Authority: AS 46.03.020
Note to HTML Version:
The Alaska Administrative Code was automatically converted to HTML from a plain text format. Every effort has been made to ensure its accuracy, but neither Touch N' Go Systems nor the Law Offices of James B. Gottstein can be held responsible for any possible errors. This version of the Alaska Administrative Code is current through June, 2006.
If it is critical that the precise terms of the Alaska Administrative Code be known, it is recommended that more formal sources be consulted. Recent editions of the Alaska Administrative Journal may be obtained from the Alaska Lieutenant Governor's Office on the world wide web. If any errors are found, please e-mail Touch N' Go systems at E-mail. We hope you find this information useful. Copyright 2006. Touch N' Go Systems, Inc. All Rights Reserved.
Last modified 7/05/2006