(a) Each permittee shall give the department written notice not less than 10 days before the start of construction on any utility facility.
(b) A copy of the permit must be at the work site during construction and installation operations and must be shown, upon request, to any department representative, Alaska state trooper, or other enforcement officer of the state.
(c) The department will, in its discretion, require inspection of the facility during construction and installation operations. The inspection must be sufficient to ensure full compliance with the provisions of the permit.
History: Eff. 5/23/82, Register 82
Authority: AS 02.15.020
Note to HTML Version:
The Alaska Administrative Code was automatically converted to HTML from a plain text format. Every effort has been made to ensure its accuracy, but neither Touch N' Go Systems nor the Law Offices of James B. Gottstein can be held responsible for any possible errors. This version of the Alaska Administrative Code is current through June, 2006.
If it is critical that the precise terms of the Alaska Administrative Code be known, it is recommended that more formal sources be consulted. Recent editions of the Alaska Administrative Journal may be obtained from the Alaska Lieutenant Governor's Office on the world wide web. If any errors are found, please e-mail Touch N' Go systems at E-mail. We hope you find this information useful. Copyright 2006. Touch N' Go Systems, Inc. All Rights Reserved.
Last modified 7/05/2006