You can also go to The Alaska Legal Resource Center or search the entire website.
If the construction professional does not respond within the time required by AS 09.45.886 , does not repair the defect to the satisfaction of the claimant within the time agreed under AS 09.45.886(1), does not provide an offer under AS 09.45.886 (2), or serves a statement under AS 09.45.886 (3), the claimant may bring an action against the construction professional for the claim described in the notice of claim without further notice.
Note to HTML Version:
This version of the Alaska Statutes is current through December, 2004. The Alaska Statutes were automatically converted to HTML from a plain text format. Every effort has been made to ensure their accuracy, but this can not be guaranteed. If it is critical that the precise terms of the Alaska Statutes be known, it is recommended that more formal sources be consulted. For statutes adopted after the effective date of these statutes, see, Alaska State Legislature If any errors are found, please e-mail Touch N' Go systems at E-mail. We hope you find this information useful.
Last modified 9/3/2005